BRIEF SCOPE:
The SOW for this project involves replacement of defective underground electrical cables (4C X 35 Sq. mm which is passing through asphalt, walkway & sandy area) from two main feeders that provide power supply to local MCC at lift station LS-334 at RWN Jubail. Conducting Testing and commissioning and restoration other associated civil works.
GENERAL INFORMATION:
Client: | MaSa – Marafiq Sour Operation & Maintenance Co |
Location: | RWN, Jubail |
Contract: | Lump Sum Contact |
Started: | 15-05-2022 |