BRIEF SCOPE:
The SOW for this project includes site preliminary works i.e Excavation, Shoring, Dewatering, Backfilling & Compaction and Construction of Urbanization Channel for around 1524 meters at SWRO Plant-2 Al-Khobar. The construction works include formwork, rebars, concreting, asphalting, and all related civil works and waterproofing & painting works.
GENERAL INFORMATION:
Client: | Acciona Agua & RTCC (JV) |
Location: | SWRO Plant 2, Al-Khobar |
Contract: | Lump Sum Contact |
Started: | 10-06-2021 |